We haven’t written about our production for a long time, but there’s a lot going on! We are currently implementing several large projects in parallel:

☛ A container transport with ready-to-install devices has set off for our client in India, and we will soon install them at the client’s premises
☛ in hall I, tanks and storage silos are going up 🏗️ ☛ in hall II, in the presence of the client, the FAT test took place, during which we had the opportunity to check our transporters and SKID devices together with the product
☛ we have completed the trial assembly of the quadruple Big Bag station. Individual elements of this station are currently undergoing abrasive blasting treatment ⌛️
☛ another customer is already waiting for our shipment, which is a screw dispenser with a screw conveyor
☛ intensive work is underway in halls III and IV, the aim of which is to deliver further components to halls I and II for further assembly
☛ hall III has been equipped with a laser welding machine, which we will write about soon

If you think that’s all… We hasten to answer that not yet! There are several smaller but equally important projects. Stay up to date with us and follow our social media!